Alberta Solar One Project
5494-6028
This project will have a generating capacity of 10.5 MW and is located 4-km west of the hamlet of Burdett, Alberta. The project will connect to FortisAlberta’s local electrical distribution grid from Burdett 386S substation via overhead power lines parallel to Township Road 104.
Solar Electricity Generation
NE-21-10-12-W4M
T0K 0J0
The following is a Google Maps feature that may not be accessible for all users. For assistance with location information, please contact: ghgregistries@csagroup.org
2021-04-01
2021-04-01
2031-03-31
Active
5
111,615
None Defined
Emission Offsets Summary
10,000
Active
11,959
Pending Retirement
0
Retired
21,959
Total 
Emission Offsets
Serial RangesType
Vintage
Year
Current Company NameEmission Offset Status
Expiry Date
Total 
(t CO2 e)
5494-6028-000-060-818-020 to
5494-6028-000-060-825-693
2023
Enbridge Pipelines Inc.
Active
2032-07-05
7,674
5494-6028-000-059-084-829 to
5494-6028-000-059-090-219
2022
Enbridge Pipelines Inc.
Pending Retirement
2031-07-05
5,391
5494-6028-000-059-090-220 to
5494-6028-000-059-092-545
2022
Enbridge Pipelines Inc.
Active
2031-07-05
2,326
5494-6028-000-059-078-261 to
5494-6028-000-059-084-828
2021
Enbridge Pipelines Inc.
Pending Retirement
2030-07-05
6,568